Project Description
Project Digital: For Clear Channel UK Ltd
Commencing: April 2015 – Ongoing
To date Twenty Twelve Civils Ltd have installed over 750 digital units on this project throughout the UK. The latest CCUK DS70 digital advertising units replacing existing poster and scroller units currently installed in the nations bus shelters and on the public footway.
The work requires the termination of the existing incoming power supply to the shelter or structure, the removal of the existing advertising unit and the construction a new re-enforced foundation.
The new unit can then be fitted, an upgraded power supply is installed and all permanent re-instatement undertaken before the shelter is brought back into service.
To enable the heavy (400kg) advertising units to be removed and re-installed, special cantilevered lifting frames and jacking bogeys were required to allow the units to be fitted ‘beneath’ the shelter roof.
New ‘free standing’ DS70 digital units have also been installed on wider footways and pedestrianised areas.
Naturally on busy bus routes having both shelters and stops out of commission for a long periods would not be possible, Twenty Twelve co-ordinated their work to enable most installations to be completed in one day.